Grove City Area - Buckeye-Pinnacle Project

As part of AEP Ohio’s continued efforts to support the Grove City area's growing energy needs, crews will install more than two miles of new underground electric line and equipment. The new equipment will help improve reliability of the electric service in your community.

We are committed to keeping you informed and minimizing the impact to nearby homes, businesses and the environment throughout the duration of this project. Please visit this page periodically for project updates.

Thank you for your continued patience as we work to improve your electric service.

Project Overview Map

The project schedule is subject to change dependent on severe weather or unforeseen circumstances.

FAQS

As part of our equipment upgrades, construction crews will install underground conduit, electric lines and other equipment as needed. Upgrades will help improve system reliability for the area.

This work will help meet existing electric needs in your community.

Work begins July 2021 and is scheduled to be complete in November 2021. The project schedule is subject to change dependent on severe weather or unforeseen circumstances.

Crews will upgrade underground conduit, electric lines and equipment along Buckeye Parkway and adjacent neighborhoods from White Road to Pinnacle Club Drive, and along Pinnacle Club Drive and adjacent neighborhoods from Buckeye Parkway to Pinnacle Woods Drive. Please see the project map above for additional detail and timing on the work being performed.

We will notify you in advance with details of any work to be performed on your property. Please confirm we have the best phone number and email address to reach you at AEPOhio.com/Account.

We do not anticipate the need for outages during these upgrades, but there is always the possibility that crews might need to take a brief outage to safely complete work. We will notify you with details in advance of any scheduled outages. Please confirm we have your best contact information at AEPOhio.com/Account in case we need to get in touch.

You may see more construction vehicles in the area. We do not anticipate road closures during construction. If temporary lane closures are needed, we will coordinate with local traffic control to minimize the impact to drivers while ensuring the safety of our crews and the community.