Loading...

Processing your request

Thank you for your patience.

Marble Cliff Project

Thank you to those who joined us at the recent community meeting to discuss our upcoming project in the Village of Marble Cliff. This work will increase our capacity to serve the growing area and meet future energy demands.

We plan to continue to work with community leaders on a number of items we discussed, including aesthetics. We’re committed to keeping you informed and minimizing the impact to nearby homes, businesses and the environment throughout the duration of this project.

Please visit this page for regular project updates and for answers to frequently asked questions.

Frequently Asked Questions

Project

We’ll be upgrading and expanding our Fifth Avenue substation in Marble Cliff. This also includes connecting our distribution and transmission lines to the new substation and removing the old substation.

This is a multi-phased project that will extend into 2022 and also includes moving Marble Cliff electric service to be powered by the new substation during a later phase. We’re committed to working with you as we move through each phase of this project and will share more information about what you can expect as plans are finalized.

Central Ohio continues to see tremendous growth and will only continue to develop. The new substation will help meet existing local electric needs and support future growth and economic development by providing greater energy capacity.

Location

The project will take place in Marble Cliff near the intersection of Riverside Drive and Fifth Avenue in central Franklin County.

With safety and cost in mind, the location’s proximity to the current station will mean minimal relocation of transmission and distribution facilities as well as minimize disruption to existing customer electric service.

Properties on the other side of Fifth Ave were considered, however, ultimately those were not for sale.

The new substation will ultimately serve areas including Grandview Heights, Upper Arlington, Marble Cliff and surrounding areas.

Community

We strive to be a conscientious community member. We’re looking at adding vegetation and other visual blocks, like fencing. Landscaping will also be installed upon completion of the substation construction. We’ll share more information on what you can expect to see from the road as it becomes available.

Temporary closures of Fifth Avenue may be required throughout the construction process. We’ll coordinate with local traffic control to minimize the impact, while working to ensure safety for the community and our crews.

While we’ll work to avoid power outages in the near-term, it's possible that they'll be required later to ensure our crews can safely complete their work. However, if an outage is planned we’ll notify you in advance.

Project Schedule

Crews plan to start pre-construction activities in early summer 2020. We’ll have more specifics on timing soon and additional phases beyond what’s listed below. The project timeline is subject to change barring any bad weather or potential COVID-19 impacts.

Phase 1

5th Avenue Site Development Construction Activities

  • Environmental remediation (Target: Complete)
  • Building demolition (Target: Spring 2021)

5th Avenue Substation Construction Activities

  • Grading site in preparation for substation construction (Target: Spring 2021)
  • Installing substation equipment (Target: Winter 2020 - Fall 2021)

Target In-Service Date: Fall 2021

Phase 2

Schedule to be determined. More information will be shared as it becomes available.

Project Contact

If you have additional questions, please contact Renee Shumate at 614-883-6790 or mrshumate@aep.com.

Welcome back!

Please login to manage your account.