Hess Station Project

We're working hard to improve your electric service.

As part of our efforts, we're upgrading equipment on two circuits to support the area's growing energy needs. This involves underground and overhead work. The upgraded equipment will help meet existing local electric needs and support future growth and economic development by providing greater energy capacity.

Our crews are trained in COVID-19 prevention and will practice safety protocols as appropriate.

Thank you for your cooperation as we work to improve your electric service. Please visit this page for regular project updates and answers to frequently asked questions.

Frequently Asked Questions

Currently, this work is scheduled to be completed without outages; however, sometimes outages are necessary for the safety of our employees, contractors and the public. If an outage is planned, we'll notify you in advance through an automated phone call. Be sure we have the best number to reach you at AEPOhio.com/Account.
Temporary lane closures of Gerrard Avenue and Grandview Avenue will be required throughout the construction process. We'll coordinate with local traffic control to minimize the impact while working to ensure safety for the community and our crews.
Work is slated to begin in late July and will take approximately four months to complete.
To reduce the spread of COVID-19 and to protect the health and safety of our customers and crews, we are taking extra caution when interacting with customers. Our crews are trained in COVID-19 prevention and will practice safety protocols as appropriate.

Project Schedule

Crews plan to start work in late July with a goal to complete in November. The project timeline is subject to change barring any bad weather or potential ongoing COVID-19 impacts.

Phase 1

  • Road and underground work on Gerrard Avenue — begins in late July and concludes in early September.

Phase 2

  • Underground work on Gerrard Avenue — begins in late September and concludes in mid-November.

Phase 3

  • Overhead work on Grandview Avenue — begins in mid-September and concludes in mid-November.

Project Contact

If you have additional questions, please contact our team at hessproject@aep.com.